BMG GmbH & Co. KG - Keithstrasse 2-4 - D-10787 Berlin | Tel: +49 (0)30 2100220

PDB III

Construction Project
Project development for the Bille power station - BT 2 - Transformer station
Location
  • Hamburg-Hammerbrook
Client
  • Kraftwerk Bille Hamburg GmbH
Planning
  • BIWERMAU Gesellschaft von Architekten GmbH
Investment volume
  • approx. EUR 20.0 million
Construction Period
  • 26 months
Contracted services BMG
  • Project development
  • Construction owner representation
Lot area
  • 12.566 m²
Footprint
  • 1.232 m²
Gross floor space
  • 6.290 m²
Gross volume
  • 21.410 m³
Storeys
  • 1st underground level to 6th floor
Utilization
  • Boarding house
  • Total rental area 4.956 m²
  • 144 rooms (at least 16 m²)
  • Common rooms
  • Storage rooms
Construction
  • Red clinker brick, masonry
  • Implementation of prefabricated bathroom pods
Design/ Fixtures
  • Service apartments
  • FF&E