PDB 106

Construction Project
Rail project Stuttgart 21- Project Section Ulm Central Station PFA 2.Sal
Location
  • Ulm
Client
  • DB Netz AG
Planning
  • ARGE Obermeyer Planen+Beraten GmbH / DB International GmbH
Investment volume
  • approx. EUR 85.0 million
Construction period
  • 2014 to 2020
Contracted services for BMG
  • Project management
  • Interface management between Technical Equipment, Line Extension and Structural Engineering
  • Contract management
  • Obtaining planning permission
Completed constructions
  • Portal structure on tunnel portal of the Albabstieg Tunnel under KienlesbergstraBe
  • Railway bridge (EU) Ulm-Aalen line
  • Railway bridge (EU) Ulm-Stuttgart line
  • Trough ramp from portal structure to the platforms
  • Reorganisation of Ulm Central Station
  • Soil excavation (V = 53.000 m3)
  • Soil improvement by soil exchange (V = 31.000 m3)
  • Installation of protective layer (V = 38.000 m3)
Special features
  • Introduction of newly built line (NBS) from Stuttgart to tracks 1 and 2
  • Converted Geislinger line tracks with connection to tracks 3 and 4 due to new NBS route
  • Connection of the NBS from Stuttgart to the western track area of the Friedrichshafen Branch
  • Modified introduction of the Aalen line into the Northern Head adapted to the NBS route
  • New building of a 5th platform west of the existing platform, with extension of the existing pedestrian underpass
  • Adaptation of the track installations of the Northern and Southern heads with diversion of the tracks to Ulm Central Station
  • New building of stair exits and elevators from the new footbridge and cycle bridge in the City of Ulm to platforms 1 to 5
Utilization
  • Incorporation of the newly built line (NBS) Wendlingen-Ulm in the Ulm Central Station
  • Exit of tracks on the west side in the direction of Friedrichshafen
  • Express connection from Stuttgart to Ulm is part of the "Magistrale for Europe"