Construction Project
Bridge Nennhauser Damm |
Location
- Berlin-Spandau, Nennhauser Damm
|
Client
- DB Projekt GmbH Knoten Berlin and Senate Administration Office for Construction, Residences and Traffic, Department XII
|
Planning
- Obermeyer Planen + Beraten, München
|
Investment volume
|
Construction period
- June 1998 to November 1999
|
Contracted services for BMG
- Section 55.8 HOAI-Property planning for engineering structures and traffic facilities,
- general construction management
- Section 57 HOAI-Local construction supervision
|
Structures constructed
- Bridge area and public traffic area (A = 3,350 m²)
- Promenade and bicycle path (A = 1,125 m²)
- Green area (A = 250 m²)
|
Special features
- Completion of street area at same time
- Adaptation of Eichholzbahn
- Landscape work, paving work
- Removal of the provisional pedestrian bridge
|