PDB 64

Construction Project
Municipal Train Duisburg, Construction Phase TA6-Los 23 and 24
Location
  • Duisburg-Duissern
Client
  • City of Duisburg
Planning
  • Metropolitan Railway Construction Office of the City of Duisburg
Investment volume
  • approx. DM 24.0 million
Construction time
  • 36 months
Activities
  • Construction management
  • Contract management
  • Technical coordination
Structures constructed
  • Two-track tunnel rectangular cross-section in open construction (L = 312 m)
  • Operating rooms
  • Pedestrian distribution levels
  • Ramp (L = 260 m) to an above-ground reversing and parking facility in dig-and-cast construction method
Special features
  • Extensive work moving lines
  • Groundwater compensation using a groundwater siphon
  • Excavation of ramp under protection of subterraneous curtains and below the reinforced concrete cover placed over it
Utilization
  • Metropolitan railway tunnel of the City of Duisburg
Construction
  • Excavation pit created from braced or rear-anchored walls
  • Watertightness of the excavation pit by integration of the subterraneous curtains in tertiary layers
  • Design of the tunnel inner shell out of concrete impervious to water in the station area using invert-wall-ceiling construction
  • Creation of ramp area out of subterraneous curtains with force-lock joining of reinforced concrete ceilings and inverts
Geology
  • Two groundwater storeys with seasonal fluctuations between 4.0 and 8.5 m
  • Fills, clay, gravel, sand, fine sand, potter’s clay
  • Chalk silt without sand inclusions respectively with sand strips and sand layers
  • Rock of the carbon