Construction Project
New Railway Construction Ebensfeld-Erfurt - Tunnel Brandkopf |
Location
|
Client
|
Planning
- ILF Consulting Engineers and OBERMEYER Planen + Beraten GmbH, Munich
|
Investment volume
|
Construction time
|
Contracted services for BMG
- Section 43.8 HOAI-General construction supervision
- Construction management
- Contract management
|
Structures constructed
- Double track tunnel tube (L = 1,493 m) with a bore of 138 m2
- Clear height/ clear width= 10.63/10.64
- Maximum cover 120 m
- Total excavated tunnel material 265,000 m3
|
Construction method
- Excavation by means of blasting resp. heading
|
Special features
- Safety concept by escape and rescue through the tunnel portals
- An additional emergency exits for this purpose, which lead into the open
- Continuous pipeline for extinguishing water in the whole tunnel
- Rescue places at the exits are linked to the transport system
|
Utilization
- Long-distance railway tunnel (design speed= 300 km/h)
|
Construction
- Full-circle mining of tunnel heading with graded heading face in accordance with the New Austrian Tunnelling Method (NATM)
- Tunnel support system by means of support arches, reinforcing steel mesh, anchors, stakes and shot-crete {d = 15-20 cm)
- Installation of a drainage to reduce ground and strata water pressure
- Sheets for waterproofing collect and direct the mountain water outside of the internal shell via sidewall drainage lines in a controlled manner
- Installation of a tunnel internal shell of water-proof concrete (d = 35-60 cm)
|
Geology
- Solid rock of the volcanic rock complex of the Rotliegende (red sediment)
- Igneous rocks, tuffs with sedimentary inclusions of clay, silt and sandstone as well as conglomerates
- Rock is covered with weathered slope rock, on which quaternary river gravel was deposited in the valleys
|