Construction Project
Railway Project Stuttgart 21 - Technical building of Main Station Stuttgart |
Location
|
Client
|
Planning
- ingenhoven architects, Düsseldorf
|
Investment volume
|
Construction period
|
Contracted services BMG
- Project management
- Construction management
- Contract management
|
Plot area
|
Gross area
|
Storeys
|
Utilization
- Supplying the underground station and parts of the Bonatz building with
- Medium high voltage 10 kV, 50 Hz
- Low voltage 400 V, 50 Hz
- Heating, ventilation and air conditioning
- Fire extinguishing water
|
Construction
|
Design/equipment
- District heating transfer stations (n = 2 x 1.5 MW)
- Recirculation air cooling unit for the internal cooling of electrical systems
- Pump stations (Q = 3,000 L/min) for the supply of fire extinguishing water
- Fire extinguishing water {V = 50 m3 )
- Medium high voltage for general and safety voltage supply network (n = 5 units)
- Transformers with a total output of 5 MW (n = 5 units)
- 400 V low voltage distribution units with outputs of 630 A to 1,250 A (n = 6 units)
- Lighting system (n = 250 lights)
- Safety lighting system (n = 170 lights)
- Fire alarm systems (n = 280 fire detectors)
- Smoke extractor systems
- Intrusion detection system
- Cables/wires for telecommunication and EDV (n = 100 sockets)
- Interior and exterior lightning protection system
|