Construction Project
Railway Project Stuttgart 21- Demolition of the former office and administration building of IHK |
Location
|
Client
|
Planning
- Klenk-Architekten Stuttgart
|
Investment volume
|
Construction time
|
Contracted services BMG
- Project management
- Construction management
- Request for proposal, award and invoicing
|
Construction work
- Removal of contaminated zones
- Gutting the interior
- Dismantling lifts, window components and exterior façade
- Demolition of existing construction and the northern retaining wall
- Disposal of building rubble and contaminated materials
- Refilling the demolition pit in compliance with ZTV-E-Stb
|
Construction method
- Careful demolition process compliant with all requirements
|
Plot area
|
Area
|
Gross area
|
Gross volume
|
Storeys
- 2nd to 1st Basement, ground floor, 1st to 7th upper floors
|
Special features
- Historic wine-growing district "Mittlerer Kriegsberg" in the neighbourhood to the north
- Protection of the neighbourhood from dust, vibrations, noise and damage
- Increased requirements for the protection of the environment, the water and health
- Preservation of transformer room in front of the building by separating cuts
|
Construction
- Strip/continuous footing and spread/isolated footing with floor plate
- Construction type: reinforced concrete skeleton frame structure
- Ceiling made of reinforced ribbed concrete floor slabs and pumice concrete blocks
- Bsmt. exterior walls made of concrete and upper floor made of red-brick and hollow blocks
- Façade cladding in natural stone and clinker brick
- Interior walls made of concrete, hollow concrete blocks and gypsum board walls
- interior staircase made of reinforced concrete
|