Railway Project Stuttgart 21- Claim management for Main Station Stuttgart |
Location
|
Client
|
Planning
- ingenhoven architects, Düsseldorf
|
Investment volume
- approx. EUR 900.0 million
|
Construction period
|
Contracted services BMG
- Verification by the claims management
- Checking content of contract
- Detecting deviations from specifications (variance analysis)
- Checking documentation of specification deviations for plausibility and completeness
- Visual inspection of correspondence and minutes of meetings
- Verification of notice of delay and disruption to the works, notice of cost over-runs and concerns
- Checking the basis for claim
- Checking how the specification deviations affect the construction period
- Checking how the specification deviations affect the construction cost
- Audit-proof verification of the supplementary offer and its reason
- Rejection of documentation and supplementary offers
- Request for additional documents
- Participation during the definition of the negotiation strategy
- Participation during the negotiation of supplementary offers
- Participation during the assignment of supplementary offers
|
Plot area
|
Area
- 55,800 m2 of which 23.659 m2 are north and south tunnel entrances
|
Gross area
|
Gross volume
|
Storeys
- Level +1: Stralsburger Platz, bay platform hall, small ticket hall in Bonatz building
- Level 0: Main traffic level, connecting axis between current downtown and new part of the city
- Level -1: Four new island platforms and Klett Passage
- Level -2: Existing main subway station (underground)
|
Utilization
- Platform hall (L/W/H = 430.00/80.00/9.00 to 12.00 m)
- Estimated 300,000 travellers per day
|