Construction Project
Construction of a soldier pile wall with concrete lagging |
Location
|
Client
|
Planning
- ACES-Arab Center for Engineering Studies
|
Investment volume
|
Construction period
|
Contracted services for BMG
- Construction supervision
- Request for proposal, award and invoicing
|
Structures constructed
- Building excavation with a depth of D = 14.00 m
|
Construction method
- Temporary construction pit support system in lower area:
- Encastre soldier pile wall embedded at either end
- HEB 360 beam, using an unsupported length of L = 5.00 m
- Concrete lagging with d = 20 cm
- Temporary construction pit support system in upper area:
- Construction pit slope without intermediate berm
- Partially secured with shotcrete sealing
|
Special features
- Using a backhoe and ripper to loosen soil
- Loading with excavator and wheel-type loader
- Trench shoring work
- Excavation area (A= 1,200 m2)
- Excavation dimensions (L/W/D = 40.00/30.00/12.00 m)
- Soil removal for a temporary ramp
|
Utilization
- Construction of a multi-storey building
|