PDB 92

Construction Project
Railway Project Stuttgart 21- Stop train Station Feuerbach
Location
  • Stuttgart - District Feuerbach
Client
  • DB Netz AG
Planning
  • SSF lngenieure AG München
Investment volume
  • approx. EUR 50.0 million
Construction period
  • 2014 to 2021
Contracted services BMG
  • Construction project management
  • Interface coordination
Completed constructions
  • New construction of dual track intercity line with
    • Open tunnel construction (I= 234.00 m)
    • Exit-and-entry trough structure designed as a ramp (L = 214.00 m)
    • Double-tracked railway bridge across Borsigstraße (L = 20.00 m)
    • Emergency vehicle access lanes
    • Pedestrian subway (W/L/H = 6.00/54.00/2.80 m), positioned below the trough structure
Special features
  • Extremely limited space for construction site equipment
  • Maintaining operation of existing intercity railway tracks
    • Relocating existing intercity railway line to the outside next to the trough structure
    • This creates open space for the trough construction
    • New construction of two single-track railway bridges across Borsigstraße
  • Trough construction intersects existing foot path
    • Replacing pedestrian subway with a new construction near by
    • Replacing the subway between platforms with new construction of staircase at Platform 2
  • Construction of two single-track railway bridges for loop lines
  • Precursory demolition of existing double-tracked railway bridge
  • Extensive partial and complete road closure with detours necessary
  • Comprehensive traffic phase planning for footpaths and traffic lanes at the Borsigstraße railway crossing
  • Preservation of the heritage-protected retaining wall
  • Lowering the intercity track by H = 6.00 m from Borsigstraße railway crossing to tunnel portal
Utilization
  • Railway feed line Feuerbach to Stuttgart main train station