PDB 109

Construction Project
Extension line Erfurt-Eisenach V200
Location
  • Erfurt, Gotha, Eisenach
Client
  • DB Netz AG
Planning
  • DB Netz AG
Investment volume
  • approx. EUR 160.0 million
Construction period
  • 2015 to 2019
Contracted services for BMG
  • Deputy BUZ management
  • Rail construction supervisor, control and safety technology (FBU LST)
  • Rail construction supervisor, superstructure and structural engineering (BUB Ob/KIB)
  • Railway operation services and safety monitoring according to VV Bau and VV BAU of the EBA
Completed constructions
  • Total section length (L = 64 km)
  • Replacement of superstructure (L = 28 km)
  • Replacement of cable container system (L = 64 km)
  • Replacement of deep drainage system (L = 10 km)
  • Replacement of catenary systems (L = 64 km)
  • Replacement of control and safety technology (L = 64 km)
  • Replacement of points (n = 30 pieces)
  • Sound insulation walls (L = 3.70 km)
  • Adaptations of the stations Wutha, Mechterstadt/Sattelstadt, Frottstadt, Wandersleben, Seebergen, Gotha, Neudietendorf, Bischleben
  • Removal of level crossing at Schonau Halt by constructing a bridge for motor traffic and the construction of a pedestrian tunnel
  • Conversion or two bridges to adapt to higher speeds
  • Replacement of emergency power systems (emergency power diesel units)
  • Internal lightning protection in modular buildings
  • Change of track geometry (L = 64 km)
Special features
  • Equipping with the European Train Control System (ETCS) as the standard train control system for European high speed traffic
  • Removal of old level crossings throughout the section
Utilization
  • Improvement in transfer conditions on the main line and on the main and regional lines
  • Hourly interval between the Berlin-Nurnberg express main line and the Dresden-Frankfurt am Main junction