Construction Project
Upgrade line Leipzig/Halle-Berlin - Track renewal between Halle and Bitterfeld |
Location
|
Client
|
Planning
|
Investment volume
|
Construction time
|
Contracted services for BMG
- Construction management
- Claim management
|
Structures constructed
- Removal of sleepers and tracks on a length of 15.0 km
- Removal of the asphalt base course
- Establishment of the new rail track as so-called non-ballasted track
- Assembly of the rails on pre-fabricated concrete slabs
|
Special features
- Work around the clock, including on public holidays and weekends
- 11 bridge constructions
- 13 points
|
Utilization
- Part of the ICE route Munich-Halle-Berlin
- Design speed after conclusion of the measure 160 km/h
- This will be followed by expansion for design speed of 200 km/h
|
Construction
- Frost protection layer (d = 50 cm)
- Hydraulically bound base course (d = 30 cm)
- Grouting made of cement mortar (d = 30 cm)
- Transversely pre-stressed prefabricated slab made of concrete C 45/55 (W/L/H = 2.55/6.45/0.20 m)
- Longitudinal coupling via GEWI steel
- Rail fastening with 10 support points per rail on a prefabricated slab
- Rail UIC 60
|